CHAPTER 1 – 1.4 – Fundamental test process- Part 1/3

  1. Recall the fundamental test activities from planning to test closure activities and the main tasks of each test activity. (K1)

1.4.1 Introduction

In this section, we will describe the fundamental test process and activities. These start with test planning and continue through to test closure. For each part of the test process, we’ll discuss the main tasks of each test activity.

In this section, you’ll also encounter the glossary terms confirmation testing, exit criteria, incident, regression testing, test basis, test condition, test coverage, test data, test execution, test log, test plan, test strategy, test summary report and testware.

As we have seen, although executing tests is important, we also need a plan of action and a report on the outcome of testing. Project and test plans should include time to be spent on planning the tests, designing test cases, preparing for execution and evaluating status. The idea of a fundamental test process for all levels of test has developed over the years. Whatever the level of testing, we see the same type of main activities happening, although there may be a different amount of formality at the different levels, for example, component tests might be carried out less formally than system tests in most organizations with a less documented test process. The decision about the level of formality of the processes will depend on the system and software context and the level of risk associated with the software. So we can divide the activities within the fundamental test process into the following basic steps:

  • planning and control;
  • analysis and design;
  • implementation and execution;
  • evaluating exit criteria and reporting;
  • test closure activities.

These activities are logically sequential, but, in a particular project, may overlap, take place concurrently and even be repeated. This process is particularly used for dynamic testing, but the main headings of the process
can be applied to reviews as well. For example, we need to plan and prepare for reviews, carry out the reviews, and evaluate the outcomes of the reviews. For some reviews, such as inspections, we will have exit criteria and will go through closure activities. However, the detail and naming of the activities will be different for static testing. We’ll discuss static testing in Chapter 3.

1.4.2 Test planning and control

During test planning, we make sure we understand the goals and objectives of the customers, stakeholders, and the project, and the risks which testing is intended to address. This will give us what is sometimes called the mission of testing or the test assignment. Based on this understanding, we set the goals and objectives for the testing itself, and derive an approach and plan for the tests, including specification of test activities. To help us we may have organization or program test policies and a test strategy. Test policy gives rules for testing, e.g., “we always review the design documents”; test strategy is the overall high-level approach, e.g. “system testing is carried out by an independent team reporting to the program quality manager. It will be risk-based and proceeds from a product (quality) risk analysis” (see Chapter 5). If policy and strategy are
defined already they drive our planning but if not we should ask for them to be stated and defined. Test planning has the following major tasks, given approximately in order, which help us build a test plan:

  • Determine the scope and risks and identify the objectives of testing: we con sider what software, components, systems or other products are in scope for testing; the business, product, project and technical risks which need to be addressed; and whether we are testing primarily to uncover defects, to show that the software meets requirements, to demonstrate that the system is fit for purpose or to measure the qualities and attributes of the software.
  • Determine the test approach (techniques, test items, coverage, identifying and interfacing with the teams involved in testing, testware): we consider how we will carry out the testing, the techniques to use, what needs testing and how extensively (i.e., what extent of coverage). We’ll look at who needs to get involved and when (this could include developers, users, IT infrastructure teams); we’ll decide what we are going to produce as part of the testing (e.g., testware such as test procedures and test data). This will be related to the requirements of the test strategy.
  • Implement the test policy and/or the test strategy: we mentioned that there may be an organization or program policy and strategy for testing. If this is the case, during our planning we must ensure that what we plan to do adheres to the policy and strategy or we must have agreed with stakeholders, and documented, a good reason for diverging from it.
  • Determine the required test resources (e.g., people, test environment, PCs): from the planning we have already done we can now go into detail; we decide on our team make-up, and we also set up all the supporting hardware and software we require for the test environment.
  • Schedule test analysis and design tasks, test implementation, execution and evaluation: we will need a schedule of all the tasks and activities, so that we can track them and make sure we can complete the testing on time.
  • Determine the exit criteria: we need to set criteria such as coverage criteria (for example, the percentage of statements in the software that must be executed during testing) that will help us track whether we are completing the test activities correctly. They will show us which tasks and checks we must complete for a particular level of testing before we can say that testing is finished.

Management of any activity does not stop with planning it. We need to control and measure progress against the plan. So, test control is an ongoing activity. We need to compare actual progress against the planned progress, and report to the project manager and customer on the current status of testing, including any changes or deviations from the plan. We’ll need to take actions where necessary to meet the objectives of the project. Such actions may entail changing our original plan, which often happens. When different groups
perform different review and test activities within the project, the planning and control needs to happen within each of those groups but also across the groups to coordinate between them, allowing smooth hand-offs between each stage of testing. Test planning takes into account the feedback from monitoring and control activities which take place through out the project. Test control has the following major tasks:

  • Measure and analyze the results of reviews and testing: We need to know how many reviews and tests we have done. We need to track how many tests have passed and how many failed, along with the number, type and importance of the defects reported.
  • Monitor and document progress, test coverage and exit criteria: It is important that we inform the project team how much testing has been done, what the results are, and what conclusions and risk assessment we have made. We must make the test outcome visible and useful to the whole team.
  • Provide information on testing: We should expect to make regular and exceptional reports to the project manager, project sponsor, customer and other key stakeholders to help them make informed decisions about project status. We should also use the information we have to analyze the testing itself.
  • Initiate corrective actions: For example, tighten exit criteria for defects fixed, ask for more effort to be put into debugging or prioritize defects for fixing test blockers.
  • Make decisions: Based on the measures and information gathered during testing and any changes to business and project risks or our increased understanding of technical and product risks, we’ll make decisions or enable others to make decisions: to continue testing, to stop testing, to release the software
    or to retain it for further work for example